98%progress! This 3 billion -phase project in Dinghu District, Zhaoqing is about to be completed!
Dinghu released 2023-12-24 17:39 Posted on Guangdong in Guangdong
good news!
Located in Yong'an Town Industrial Cluster District, Dinghu District
New progress in Zhaoqing Dinghu Natural Gas Thermal Power Union Project (Phase I)! The project has now entered the end of the closing, and the trial production is about to be completed!
It is understood that the project was constructed and operated by Guangdong YuedianYongan Natural Gas Thermal Electric Co., Ltd.
The total area is about 170,000 square meters,
A total of two stages of construction, including 4 gas, steam combined circulating heat -cooled heat production units and supporting thermal network engineering construction.
The first phase of the first phase of the project of Zhaoqing Dinghu Natural Gas Thermal Power Union project was about 3 billion yuan, and construction was officially started on December 10, 2021. As of now, the progress of the first phase of the project has been completed by 98%.
Among them, 99%of the main construction projects were completed, and the civil construction and installation work generally entered the ending stage, and the equipment of each group was entering the intense debugging link.
It is reported that the project uses natural gas as the fuel and uses gas -steam circulation to achieve green low -carbon energy supply. The energy utilization rate is greatly improved compared to conventional thermal power units.
After the project is officially put into operation, it is expected to run 3,000 hours a year, 29 billion kWh can be generated, and heating 560 tons/hour. It will further alleviate the central heating pressure of the industrial agglomeration area of Yong'an Town, and replace the dispersed small boilers, save bidding coal, reduce carbon dioxide , Sulfur dioxide emissions, reducing ash and dust emissions, etc., have significant efficiency of energy conservation and emission reduction. It is of positive significance for helping to achieve the "double carbon" goal, promoting the replacement of coal reduction in the Guangdong -Hong Kong -Macao Greater Bay Area and the adjustment of the energy structure of our province.
At the same time, after the project is officially put into production, it will attract a large number of enterprises in our district to settle in, and further drive the construction of people's flow, logistics and infrastructure construction, and promote the construction and development of the industrial park in Dinghu District.